top of page

NEWS

10.02.23

P1029907.JPG
We have loaded 3rd of 4 ships with the prefabricated concrete walls which were delivered to Kalundborg, Denmark

Where Per Aarsleff A/S is involved in construction of four new facilities for Novo Nordisk. The last ship with walls is scheduled to be delivered in week 25, 2023.

16.12.22

DJI_0851.JPG
We have started manufacturing the first TP less concrete working platforms for Ørsted.

 

It is total of 106 that will be used in the construction of two Ørsted offshore wind farms in Germany, Gode Wind 3 (242 MW) and

Borkum Riffgrund 3 (900 MW).

The production has started on 1st of September 2022 and we have already casted 34 platforms by now, reaching the desired rythm of casting 3 platforms per week. Aarsleff BIZ is also responsible for production and mounting of aluminium railings, upper external ladder and Davit Crane installation and load testing as well as the Low Voltage scope.

 

The first mock up platform was delivered to Lindø, Denmark in October and the deliveries of the remaining scope is planned between April and July 2023.

17.09.22

P1014744.JPG
Between March and August 2022 we have produced 45 pcs of big elements for new quay wall in Hargs Hamn, Sweden.

We have done 23 pcs of 14,6m heigh L-walls of weight in range 270-307 tons and another 22 pcs of middle walls which goes in between the L-walls (weight 45-76 tons). The elements were produced and delivered on site on Marine Group barge Carrier 16. After spectacular submerging operation the elements were unloaded from barge and installed by Lodbrok crane within 3 weeks. This is how 220m of new quay line appeared in Hargs Hamn.

01.08.2022

1st of August we have comissioned and received permit to use for the new giant equipment. 

The gantry will lift 250 tons, the span is 40m, drive on 250m long tracks and lift up to 40m height. It is a huge reinforcement of our lifting and production capabilites of the large elements such a concrete working platforms for offshore windmill market and many others.

17.03.2022

DJI_0741.JPG
DJI_0727.JPG
DJI_0029.JPG
P1711324.JPG
We have successfully concluded a project with @SGRE for the production of 356 concrete beams for storage of wind turbine nacelles in Cuxhaven and Rotterdam.

The elements were delivered within time and according to project quality specifications. We are furthermore delighted that we secured a further delivery of 500 of these prefabricated concrete elements with SGRE.”

14.03.2022

Skylight 04.JPG
Skylight 06.JPG
Skylight 01.JPG
Skylight 05.jpeg
We have finalised production of all elements for Statens Naturhistoriske Museum in Copenhagen.

The last and the most challenging elements were 8 pcs of skylights which will be installed in the roof of Museum. The ellipse shaped in top view and  truncated cone in cross-section, casted in the wooden formwork cut by CNC and installed in tilted position to the roof surface. We have never before produced such a fancy thing. Just look at this.

04.01.2022

P1711509.JPG
DJI_0082.JPG
DJI_0570.JPG
DJI_0575.JPG
We have produced 2 pcs of 500 ton caissons which were delivered to Gothenburg’s in Sweden harbour in December 2021

After arrival the caissons were submerged and transported to the project site in Trollhättan by the tugboats. After placement on the sea bed the top part of the caisson’s walls were casted and the chambers were backfilled.

  • North Caisson – 170m3 – 425 tons

  • South Caisson – 190m3 – 475 tons

07.09.2021

P1688566.JPG
DJI_0671.JPG
P1699278.JPG
We have produced the first prototype hybrid concrete/steel platform SKYBOX LITE for SIF Group.

he platform is constructed as concrete round beam with the conical shape of the inner ring casted with the tollerances of +/-2mm. The secondary steel structure and the railings is made os black steel with CX anticorosion protection. The platform was loaded and delivered to Netherlands on special trailer.

 

  • Platform dimensions 6,6 x 6,0m x 1,38m

  • Platform weight 13,75t

19.08.2021 

P1688455-HDR.JPG
DJI_0564.JPG
P1688597-HDR.JPG
P1688537-HDR.JPG
Busy vacation this year. We are running parallel several projects.

Starting from production of small pile caps (2400pcs of 900kg/pcs) going through production of edge bridge beams and road barriers for Swedish Implenia, casting the heavy beams and slabs for Tunnel stations in Copenhagen, starting production of 336pcs T-shaped storage rack for Siemens, ending up on production of two 700t caisons produced on barge (11m diameter, 10m heigh) and also 8 pcs of moon shape foundation beams of 18 ton weight. Our favorite offshore works are ongoing on prototype Skybox lite platform for SIF. We have also purchased new lifting heavy duty harbour crane Sennebogen 6180 to manage an arising number of lifting operations we are performing each day.

16.04.2021

DJI_0338.JPG
P1633371.JPG
P1633456.JPG
Last Friday 16.04.2021 we have loaded out and shipped away concrete elements of the first station for the Cityringen – Branch off to Sydhavnen Metro Project in Copenhagen.

The elements for one station consists of 9 pcs of V-beams and 61 pcs of heavily reinforced roof slabs which will be
mounted on top of the beams. In total we have to produce 45 beams of weight 55-65t per beam and
273pcs of roof slabs. The part of our service for that project is designing works and 3D modeling of
each item in TEKLA software.

28.02.2021 

DJI_0864.JPG
DJI_0877.JPG
DJI_0113.JPG
DJI_0093.JPG
Now its official - the last batch of 25 maintenance free Concrete Work Platforms for the Hornsea Two Offshore Wind Farm, has left our certified concrete element factory in Poland

All produced according to specifications and time schedule.

21.01.2021 

P1611126.JPG
P1599574.JPG
P1599561.JPG
P1611227.JPG
We start deliveries of the precast wall element for the Statens Naturhistoriske Museum in Copenhagen where Per Aarsleff A/S ia a general cotractor.

In total we will produce 581 pcs of walls until August 2021.

14.01.2021

P1600911.JPG
P1600861.JPG
P1600930.JPG
DJI_0473.JPG
Today we have loaded and delivered the first ship with cable chambers to Odense site of our mother company Per Aarsleff A/S.

In total we will produce over 400 pcs of chambers and deliver them until end of July 2021. Total concrete volume would be 5 000m3 with a total weight 9 500t.

The chambers will be outfitted with ladders, cable watertight ducts, safety brackets, pulling eyes, cast-in channels, earthing terminals, dewatering pipes, gratings etc”

04.10.2020 

DJI_0064.JPG
DJI_0048.jpg
DJI_0059.JPG
P1500283-HDR.JPG

Today we have sail out with the record breaking number of 25 Concrete Working Platforms on one barge.

The 3rd batch (5 in total) of Hornsea Two CWPs is on its way to Aalborg where BLADT Industries utilize them on their TPs.

22.09.2020 

DJI_0217.JPG
P1522741.JPG
DJI_0226.JPG
P1522738.JPG

We have started production of slab-track elements for Danish railway project Hovedstadens Letbane.

We will produce total quantity of 3769 pcs of slab tracks and supporting beams of total length of over 11 000m and  8225 m3 of concrete. The cargo will weight almost 20 000 tons and will be delivered within the year by 10 pcs of sea coasters.

Today we have loaded the first ship.

 

1806 pcs of not-embedded types

1963 pcs of embedded types

4000 pcs of supporting beam 3,0 x 0,2 x 0,2m

19.09.2020 

DJI_0018-2.JPG
DJI_0009-2.JPG
P1566070.JPG

Today the 1st load-out of the Concrete Work Platforms (CWPs) for Windpark Fryslân took place at our certified precast concrete element factory.

Each CWP weighs 76 tons and will in the next weeks be installed by Van Oord on the Monopiles in the IJsselmeer. Thanks for all involved parties (Van Oord & Spliethoff) and personnel for a smooth operation!

CWPs are a cost effective, maintenance free and durable solution for the MP/TP & TP-less MP foundations of your OWF.

05.08.2020 

P1488331.JPG
DJI_0600.JPG
DJI_0562.JPG
DJI_0117.JPG

We have finished production of 40x40 concrete precast piles for our sister company AARSLEFF Sp. z o.o. for the neibourhood job site in Swinoujscie.

We have produced 868 piles of single lengths 16-18m and total length of 15 150m and concrete volume of 2423m3.

The piles were produced at our facility in Swinoujscie, loaded to the barge and towed to the Aarsleff Sp. z o.o. piling job site at ferry terminal in Świnoujście. The advantages of ONE COMPANY cooperation was: the closeby production of good quality piles, possibility of producing piles without a joint and a efficent productivity of driving the piles on site.

22.07.2020 

DJI_0707.JPG
DJI_0702.JPG
DJI_0708.JPG

During last two days we have made another load-out for Hornsea Project 2 Wind Farm. It’s now 2nd batch for BLADT (and 4th overall) of concrete working platform which will be delivered to Aalborg in August 2020.

The platforms are equipped with the aluminium railings, Davit crane and electrical equipment. We have used our 150t RTG crane to drive them from the storage area next to the quay wall when the 260t floating crane pick them up and place on the barge. Together with Fryslan platforms we have now 100 pieces! of concrete working platforms for offshore industry stored at our site in Swinoujscie.

21.07.2020 

DJI_0003-2.JPG
P1499454.JPG
DJI_0634.JPG
DJI_0560.JPG

AARSLEFF BIZ Has delivered total amount of 3800m3 of large concrete blocks for offshore industry. The elements has been produced in amazingly short time of 4 weeks for out client Modern American Recycling Services Europe in port of Fredrikshavn

Production of 263 pieces of blocks has started in very short notice. We have produced variety of 6 types of blocks in weight range of 20 up to 170 tons (first blocks) in total weight of 9000 tons/ The blocks were delivered in two batches after 4 and 5 weeks since works commencement on board of sea barge carrier 17 and ship. The elements up to 70t weight were produced in 20 molds and two heaviest elements of 170t were casted directly on barge. The elements delivered to M.A.R.S. Europe in Fredrikshavn will be used as a load spreading blocks for skidding lane for Tyra East and West platforms of weight 16 500 tons to be moved on land for scraping. AARSLEFF BIZ has also designed and delivered rigging set to be used for unloading and repositioning of blocks. 

26.06.2020 

P1488568.JPG
P1488604.JPG
DJI_0459.JPG
P1488620.JPG

Aarsleff BIZ together with client Van Oord carried out a Mock-up test of the Fryslan OWF Concrete Work Platforms (CWPs).

The purpose of the – successful executed - CWP Mock-up test was to simulate all the steps of Van Oord operations regarding the lift and installation of the CWP as they are planned to take place during offshore operations later this year.

 In that regard the installation methods, the lifting/rigging plans, EPIC (External Platform Installation Cone) installation guide, tag lines and winches were assessed to avoid potential mistakes prior to Van Oord’s offshore works execution.

Additionally, the Mock-up CWP (which also will be installed offshore) was weighed with loadcells to verify the design weight.

26.05.2020 

We are ongoing with production of 89 pcs of 75 ton cwps for Fryslan wind farm 

We are planning to finish the project till the end of October. The platforms will be delivered on site in four batches by self loading ships. 

P1477722.JPG
23.04.2020

Today we have sailed out two giant 2000t concrete caisons to the Port of Ystad.

They will be directly submerged from the barge and placed on the designed location during coming weekend. The production lasted since November 2019. See video from this project in the project tab.

DJI_0705.JPG
10.04.2020

Today we have completed last major milestone in constructing two 2000 ton caissons for Ystad Harbour

We have installed deck elements on both caissons, each consisted of 4 precast concrete elements weighing 60 ton each. Operation took several hours without the need of rotating of the barge.

DJI_0446.JPG
23.03.2020

We have delivered full ship with the elements for the Expansion of Port of Skagen — Phase 3.

The concrete precast elements are front wall elements of the quay wall, suitable for both sheet pile walls and combi walls (371 units). Besides that we have produced 50 units of 15m and 18m long reinforcement steel cages ready to install in the new quay wall construction. In total we have delivered 850 tons of concrete and reinforcement steel elements.

  • 115 pcs of L-walls combi-wall

  • 256 pcs of L-walls sheet pile wall

  • 44 pcs of 18m reinforcement cages

  • 6 pcs of 15m reinforcement cages

  • 96t of loose reinforcement steel rebars

DJI_0183.JPG
04.03.2020

AARSLEFF BIZ ongoing with production next 2 giant 18m high caissons.

2000t structures to depart in April 2020 and to be submerged at the port of Ystadt.

DJI_0005.jpg
09.12.2019 

OFFSHORE CONCRETE WORKING PLATFORMS in 2020

„We are pleased to announce that we have been awarded with 2 offshore contracts for production of CWP in 2020. We will produce 165 pcs of platforms for Hornsea 2 Project in UK as well as 89 pcs for FRYSLAN Project in Netherlands. It is a big challenge for us and require an extreme casting schedule of one platform each working day.”

DSC_3027.jpg
03.12.2019 

YSTAD HARBOUR

We have performed the skidding operation of 2 heavy reinforcement cages XXX ton each on Carrier 16 barge deck. This operation will begin the on-barge production of two Caissons structures (2500t each) for Ystad harbour. The plan is to completely fabricate, deliver and submerge the caissons before May 2020.

DJI_0020-2.JPG
24.10.2019 

COASTAL VIRGINIA OFFSHORE WINDFARM

 „AARSLEFF BIZ has produced and shipped 2 trial offshore concrete working platforms for US Coastal Virginia offshore windfarm. The platforms were shipped to Rostock were our installation team have assembled aluminum railings and other outfitting accessories.”

2 pcs of 90t offshore concrete working platforms for the US market

DSC_4502.JPG
06.10.2019 

COPENHAGEN AIRPORT

„We have loaded and sent out the last 3 ships with 43 pcs of special precast tunnel elements for the Copenhagen Airport. The 32 ton elements will be shipped to Koge harbour where they will be unloaded on trucks and transported directly on Copenhagen Airport site. We have produced 118 pcs of elements of 7 different sizes. Total of 3760 tons of element delivered on 3 ships within 2 months. 

P1422505.jpg
26.08.2019 

HANSTHOLM CUBIPODS

„The production of Cubipods’ is over. We have produced 3452 pcs of various elements with 22 000 m3 of concrete volume and 62 000 t total weight. Since May 2018 we have loaded and shipped 8 north sea barges to Denmark for Hansthom harbour expansion Project.,

P1433548.JPG
19.07.2019 

CARLSBERG TOWER

„We have started a serial production of prefabricated concrete columns for 120 meters high Carlsberg Tower which will become the tallest residential building in Copenhagen”. 

Production of precast concrete columns for:
⦁    Parking house: 789 pcs
⦁    Tower: 746 pcs
Concrete strength: C60/75
 

P1433503-HDR.JPG
18.06.2019 

HANSTHOLM CAISSON

„Aarsleff BIZ just sent its biggest concrete element so far (16m high, 40m long, 23m wide and ca. 7.000 tons heavy) to Denmark (Hanstholm harbour). Watch our movie showing the production process.

DJI_0078DXG.jpg
13.06.2019 

YSTAD HARBOUR

„Aarsleff BIZ has started the production of various concrete precast elements for the Ystad harbour in Sweden. The plan is to deliver full range of elements, starting from small sized units like: anchor plates, quay wall front wall elements, going through light mast foundations, wells and ending up on 2 large scale Caissons of 2300 tons each”. This week we have loaded 129 pcs of anchor plates.

Production of:

  • Anchor plates: 129 pcs

  • Quay wall front wall elements: 151 pcs

Wells: 40 pcs

  • Light mast foundations: 37 pcs

  • Caissons: 2 x 2500t
     

DJI_0015.JPG
05.06.2019 

URBAN RIGGER