MASNEDSUND BRIDGE

  • Production of 200m long of precast concrete railway bridge in 8 months

  • 5 piers and 6 bridge decks, each of weight more than 1000 tons

  •  4500m3 of concrete

  •  1000 tons of reinforcement steel

  •  19 pcs post-tensioned cables on each deck installed

  • Delivered to Masnedsund, Denmark on two AARSLEFF 10 000 tons sea barges